Hi Rakesh,
Thanks for your valuable reply. Solution seems really interesting to me. But few points , mentioned below in colored , are not very clear ..
Here my doubt is -
(1) If I create 8 user status for my equipment (S001--> 1st Hr, S002-- > 2 nd Hr....etc), which status will be read by the user Exit IWO10009 and when ? means What logic would be applied at the time of selecting the particular status ?
(2) How system will read the total no. of Hours available , if available hours are more than 8 e.g. 2-3 days capacity is available in future?
(3) Also since I need to do advance planning, with this Equipment, means need to check when it'll be available in future ,how can we get the exact dates on which these hours are available??
Will really appreciate, if I can get a detail description on this..